Most families who extend want the same thing: a bigger kitchen and living space that opens onto the garden. How you get there depends on the size of extension you need and what the rules allow on your street. This guide sets out the permitted development limits, the main types of extension, and what each one costs.
Permitted development: the rules in short
Houses in England have permitted development rights, which allow some extensions without a planning application. For a single-storey rear extension, the main limits are:
- it can project up to 3 metres from the original back wall of a terraced or semi-detached house, or 4 metres on a detached house;
- under the council’s prior approval process, those limits rise to 6 and 8 metres. The council writes to your neighbours and considers their comments before deciding;
- it can be no more than 4 metres high, and no more than 3 metres high at the eaves if it is within 2 metres of a boundary;
- the materials should look similar to the house; and
- together with other buildings, it must not cover more than half of the land around the original house.
A single-storey side extension is allowed up to 4 metres high and no wider than half the original house. A two-storey rear extension can project up to 3 metres, if it stays at least 7 metres from the rear boundary.
These rights do not apply to flats or maisonettes. In conservation areas, side extensions and extensions of more than one storey need planning permission, and some councils remove other rights with Article 4 directions. “Original” means the house as it was built, or as it stood on 1 July 1948, so earlier extensions count against the limits.
The main types of extension
Single-storey rear extension
The most common project. A typical extension of 20 to 30 square metres creates a kitchen-diner across the back of the house, with wide glazed doors to the garden. Guide price: £65,000 to £110,000 including VAT (about £3,000 to £4,000 per square metre), 12 to 16 weeks on site.
Side return extension
On Victorian and Edwardian terraces, the narrow passage beside the rear outrigger is often wasted. Building into it widens a galley kitchen into a full-width room, usually with glazing in the roof to bring light into the middle of the house. Guide price: £45,000 to £70,000 including VAT, 9 to 12 weeks.
Wraparound extension
A side return and a rear extension built together, wrapping around the corner of the house. It gives the largest ground floor space, typically 30 to 40 square metres. Guide price: £100,000 to £150,000 including VAT, 14 to 20 weeks.
Double-storey extension
Extending on two floors adds a kitchen and living space downstairs and bedrooms or a bathroom above, for not much more than the cost of building the foundations and roof once. It usually needs planning permission. Guide price: £110,000 to £160,000 including VAT for about 40 square metres over two floors, 16 to 24 weeks.
Planning permission: when you need it
If the extension goes beyond the permitted development limits, the house is in a conservation area, or it is a flat, you need a householder planning application. The council usually decides within eight weeks. It looks at the design, the effect on the neighbours’ light and privacy, and how the extension fits the street. A well-drawn scheme that follows the council’s own guidance is far more likely to be approved first time.
If your extension is permitted development, we still recommend a lawful development certificate, which confirms the work was lawful when you come to sell.
Building regulations and party walls
Every extension needs building regulations approval: foundations, structure, drainage, insulation, fire safety and ventilation are all checked, and you receive a completion certificate at the end. If the extension is built on or near a boundary you share, the Party Wall Act requires you to serve notice on your neighbours, usually two months before work on a party wall, or one month before digging foundations near theirs and deeper than them.
How long does it all take?
Allow for the design and approvals before the build: a few weeks for drawings, up to eight weeks for a planning decision or a lawful development certificate, and party wall notices served in parallel. Once on site, the build times above apply, with a programme agreed in advance.
The fastest way to know what your house can take is a survey. Ours is free, we check the planning position for your street, and the quote that follows is itemised.