A full renovation goes well or badly depending on the order the work is done in. Fit the kitchen before the rewire and it comes out again; plaster before the pipes are in and the walls are chased twice. This guide sets out the order we follow on every renovation and what each part costs.
1. Survey and plan
Everything starts with understanding the house: its structure, the state of the wiring, plumbing and roof, any damp, and what you want the rooms to do. Decisions about layout are made now, because moving a wall or a bathroom later is expensive. If walls are coming out, a structural engineer designs the beams at this stage.
Internal work rarely needs planning permission, but a listed building needs listed building consent for internal changes, and flats usually need the freeholder’s consent under the lease.
2. Strip-out
Old kitchens, bathrooms, flooring, and sometimes plaster are removed. This is when hidden problems show up: rotten joists, old lead pipework, or wiring that has been extended badly over the years. A good quote includes an allowance for what the strip-out might reveal, and explains it.
3. Structural work
Steel beams for knock-throughs, new openings, repairs to joists and floors, and any underpinning are done next, signed off by building control. This is the noisiest and dustiest stage, and the one where living elsewhere makes most sense.
4. First fix
New cables, pipes and ducts go in while the walls and floors are open: the rewire, the new heating pipework, soil pipes and waste for bathrooms, and any underfloor heating. Electrical work is certified by a registered electrician and gas work by a Gas Safe registered engineer, both logged with the council for you.
5. Plastering and floors
Walls and ceilings are boarded and skimmed, or replastered, and screeds are laid. Plaster needs time to dry before decorating, so the programme allows for it.
6. Second fix and finishes
Kitchen and bathroom fittings, sockets and switches, radiators, doors, skirting and architraves go in, followed by flooring and decoration. Snagging at the end catches the small things before handover.
What it costs
| Work | Guide price, including VAT |
|---|---|
| Full renovation, 3-bed terrace (about 80 m²) | £57,000 to £63,000 |
| Full renovation, 3-bed semi (about 95 m²) | £68,000 to £75,000 |
| Full renovation, 3-bed detached (about 130 m²) | £93,000 to £102,000 |
| Medium renovation, 3-bed (new kitchen and bathroom, partial rewire, replastering, decoration) | £30,000 to £45,000 |
| Cosmetic refresh, 3-bed (redecoration, new flooring, minor repairs) | £10,000 to £20,000 |
| Full rewire, 3-bed house | £8,000 to £10,000 |
| New boiler, pipework and radiators | £5,000 to £9,000 |
| Replastering, whole house | £5,000 to £9,000 |
| Windows, whole house (uPVC double glazing) | £6,000 to £11,000 |
| Kitchen (mid-range, supply and fit) | £10,000 to £20,000 |
| Bathroom (full refit) | £5,000 to £9,000 |
A full renovation covers the strip-out, rewire, replumb, new heating, replastering, kitchen, bathroom and floors. Your own price depends on the house and your choices, so it comes in an itemised quote after a survey.
Can you live in the house?
For a cosmetic or medium renovation, often yes, room by room. For a full renovation, the strip-out, structural work and first fix leave the house without a kitchen, a bathroom or heating for weeks at a time, and most families move out for that part. We agree the programme with you before work starts, so you can plan around it.