Planning permission and building regulations are often confused, but they are separate systems with different purposes. Most home projects need building regulations approval; many do not need planning permission. Here is what each one covers, along with the other consents that often come up.
Planning permission: what you build
Planning is about the effect of a building on its surroundings: its size, appearance, use, and the impact on neighbours and the street. Applications go to your local council, and a householder application is usually decided within eight weeks.
Permitted development
Houses have permitted development rights, which allow some extensions, loft conversions and outbuildings without a planning application, within set limits. These rights do not apply to flats and maisonettes, are reduced in conservation areas, and can be removed by the council with an Article 4 direction.
Lawful development certificate
If your project is permitted development, you can apply for a lawful development certificate. It is not compulsory, but it is the council’s confirmation that the work was lawful, and buyers’ solicitors usually ask for it when you sell.
Prior approval
Larger single-storey rear extensions, up to 6 metres on a semi or terrace and 8 metres on a detached house, go through prior approval. The council notifies the neighbours and decides whether the impact is acceptable.
Listed buildings and conservation areas
A listed building needs listed building consent for any work that affects its character, inside or out. In a conservation area, more types of work need planning permission, and demolition of most buildings needs consent.
Building regulations: how you build it
Building regulations set minimum standards for the construction itself: structure, fire safety, insulation and energy use, ventilation, drainage, stairs, electrical safety and access. They apply whether or not planning permission is needed. Extensions, loft conversions, structural alterations, new bathrooms with new drainage, and replacement windows are all covered.
Approval comes from your council’s building control team or a registered building control approver. You can apply with full plans, which are checked before work starts, or a building notice for simpler jobs. Inspections take place at key stages, and you receive a completion certificate at the end. Keep it: you will need it when you sell.
Some work is self-certified by registered installers instead: electrical work by a registered electrician, gas work by a Gas Safe registered engineer, and windows by a FENSA registered installer. They notify the council for you.
The Party Wall Act
If you build on or next to a wall shared with a neighbour, cut into a party wall, or dig foundations close to a neighbour’s, the Party Wall etc. Act 1996 requires you to serve notice: two months before work on a party wall, and one month before building a new wall on the boundary or digging within 3 metres of a neighbour’s building and deeper than its foundations. If the neighbour does not agree, surveyors prepare an award that sets out how the work is done.
Other consents to check
- Leases and freeholders: flats, and many houses on private estates, need the freeholder’s consent for alterations.
- Trees: work to trees covered by a tree preservation order, or in a conservation area, needs consent or notice to the council.
- Highways: skips, scaffolding and parking suspensions on the road need licences from the council.
- Build over agreements: building over or near a public sewer needs the water company’s agreement.
We handle all of these as part of every project: the planning route, building control, party wall notices and the licences for the street, so you are not left to work them out on your own.